Building work started in November.
This page will be updated at regular points throughout the project. Be sure to check back regularly !
- Before
This is how the front of the building looked before work started.
The gas tank had been moved but the electricity pole is still in place, due to be moved on 29th October.

- November Update
It was an exciting day when the builders arrived as scheduled to begin work on the Parish Hall extension and got to work demolishing the porch. Unfortunately this revealed two big cracks in the wall of the main hall. So worked stopped. However, the all clear to continue was given after a building surveyor inspection and the project is back on track. The next step for the Parish Hall Trust is to bury the time capsule in the foundations. This records the state of the parish in this pandemic year for posterity.

Due to Covid, the hall has been closed to users during the November lockdown, but it is hoped that it can be re-opened in early December subject to government guidance on safety and hygiene. Bookings can go-ahead despite the building works, which are all exterior at this stage.
To book, please see http://castlemortonparishhall.org.uk/, or email manager@castlemortonparishhall.org.uk
- Work started
The electricity pole has been moved to a more convenient location, and the front porch removed.

- Foundations laid
The 1m deep foundations for the extension have been laid.
The beams to support the floor go in next week.


- Time Capsule
Before the work got too far advanced, we buried a Time Capsule under the floor, so that future generations can see a record of what 2020 had been like for us all.

- Rising Up !
The floor beams have been laid and the walls are starting to come up. There were a few delays caused by availability of materials, but it’s starting to happen at last.



- Exterior walls


- Roof

- Erecting a tent
Working with the builder, we have agreed to erect a tent over the building to allow work to continue during the bad weather. This went up on Friday.

- A peek under the hood


- Rubber roof going on

- Meeting Room interior
Here you can see the meeting room taking shape. The area in the corner is for the accessible toilet and a storage cupboard.

- A peek inside
The access ramp is coming along, and with the interior plastered, we can start to get an idea of how light it will be in the extension.


- Roof going on !


- Windows and Doors
The windows and doors finally arrived last week, and are being fitted.


- Rendering
The walls get rendered, then a colour coat will be added after a week or two.

- Nearly Finished
Just a few items to finish. And some locals have come to admire the new extension!


- Final Touches
The final touches were the aluminium cladding and the blinds.