November Update

It was an exciting day when the builders arrived as scheduled to begin work on the Parish Hall extension and got to work demolishing the porch.  Unfortunately this revealed two big cracks in the wall of the main hall.  So worked stopped.  However, the all clear to continue was given after a building surveyor inspection and the project is back on track.  The next step for the Parish Hall Trust is to bury the time capsule in the foundations.  This records the state of the parish in this pandemic year for posterity.

Due to Covid, the hall has been closed to users during the November lockdown, but it is hoped that it can be re-opened in early December subject to government guidance on safety and hygiene.  Bookings can go-ahead despite the building works, which are all exterior at this stage.